LBN 261-15 names them among the documents attached when a building is accepted into use. In Riga and the Riga region we visit sites where the work is not yet covered and tell you which documents can be prepared.
What concealed works are in an electrical installation
Concealed works are those that later work will hide from view. In an electrical installation these are, for example, cables in wall chases and under plaster, cables in the floor or ceiling, a cable in a trench to a garage or sauna and the earthing loop in the ground.
Point 53.3 of LBN 261-15 requires concealed works acceptance records on the installation of electrical equipment to be attached to the building acceptance statement, if such works have been done. In Riga, the document list of the city’s acceptance service mentions acceptance records for significant structures and concealed works.
Checked on 25 November 2026: LBN 261-15 point 53.3 (likumi.lv/ta/id/274674), Riga municipality building acceptance service (riga.lv).
When the record has to be drawn up
| Work | When the record is drawn up | What covers it |
|---|---|---|
| Cables in wall chases | Before plastering or filling | Plaster, tiles |
| Cables in the floor | Before the floor is poured | Concrete layer |
| Cables in frame walls and ceilings | Before the plasterboard is fitted | Cladding |
| Underground cable to another building | Before the trench is backfilled | Soil |
| Earthing loop | Before backfilling | Soil, foundations |
Who signs the record on your site depends on whether there is a construction works manager and a construction supervisor. Find this out from the building authority or the construction works manager before the work is covered.
What is worth writing in a concealed works record
If the construction works manager or the building authority has its own form, use it. In any case it matters that one can later understand from it exactly what was covered. For the record to be useful both to the building authority and to the next electrician, it is worth stating in it:
- the room and the part of the wall or floor where the work was covered;
- the cable type and cross-section, the locations of boxes and joints;
- which distribution board circuit the cable comes from;
- the date the work was examined and who examined it;
- annexes: a diagram or sketch and photos with dimensions.
For an earthing loop, the number and layout of the earth electrodes is also useful in the record, because after backfilling this can only be established by measurements.
If the walls are already closed
A concealed works record is not recreated after the work has been covered; the building authority has to be asked what it accepts instead. We do not sign records for work that cannot be examined, and we do not prepare documents with an earlier date.
What can still be done after covering are measurements: insulation resistance, phase-neutral loop, earthing and bond resistance (points 53.4 and 54 of LBN 261-15), as well as a diagram of the electrical installation as built. Whether the building authority accepts them in your case instead of concealed works records has to be asked at the building authority.
How to prepare while the work is still visible
- Plan the time Request a site visit before the plasterers or floor layers start work, not on the same day.
- Take photos It is worth photographing the routes on each wall yourself with a tape measure, so that you later know where the cables run.
- Gather the papers Conformity declarations for cables and equipment and the design, if there is one.
- Write it in the form Which work will be covered, when the finishing is planned and who is asking for the records.
How much a site visit before covering costs
- As-built diagram / distribution board diagram: price after the site visit
- Site visit: €40
- For a private house: measurements and documentation for putting a private house into use from €230
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. After the site visit we tell you which documents can be prepared and what the price will be.