We carry it out in flats, private houses, business premises and apartment buildings in Riga and the Riga region. Which measurements are needed depends on who is asking for the document: the building authority for putting into use, the fire safety regulations for a periodic inspection, or you yourself before buying or renting out.
The electrical installation measurements that make up the test
Electrical measurements are not a single figure. LBN 261-15 and the fire safety regulations currently in force (Cabinet Regulation No. 238) name several separate measurements, and each has its own meaning.
- Insulation resistance measurements: whether the wire insulation meets the minimum values set in Annex 6 of LBN 261-15. The building standard requires this measurement before putting into use.
- Phase-neutral loop measurements: the total impedance of the circuit from the phase conductor to the neutral conductor, which determines whether the protective device will disconnect the circuit at the moment of a fault.
- Earthing resistance measurements: the resistance of the earthing installation and the connection between the earth electrode and the parts to be earthed.
- Residual current device (RCD) testing: whether the residual current device disconnects the circuit at the specified residual current.
- Lightning protection testing: for buildings that have a lightning protection system.
- Thermal camera inspection of a distribution board: the quality of the contact connections in the board, which Regulation No. 238 requires to be checked together with the periodic inspection.
Electrotechnical measurements for a single line, for example insulation only or earthing only, are possible. Sub-point 53.4 of LBN 261-15 and the periodic report under Regulation No. 238 include several measurements together, so first find out who will ask for the document.
Testing by property: flat, house, business
If the document is required not by a particular regulation but by a situation, choose the page by property type. Electrical installation testing in a flat is the page for after a renovation or before selling or renting out. Electrical installation testing in a private house also covers a sauna, garage and outbuilding if they are fed from the house distribution board.
For owners and tenants of offices, shops, warehouses and production sites there is electrical installation testing for businesses. For property managers and flat owners’ associations there is electrical installation testing in an apartment building: the incoming distribution board, stairwell boards and common areas.
Electrical installation test documentation: who requires it
The name of the document depends on the regulation that requires it. The table shows the most common situations and the laws and regulations in which the document is named.
| Situation | Regulation | Document | Page |
|---|---|---|---|
| A self-built Group 2 residential building is put into use | Cabinet Regulation No. 529, points 157.7.1 and 168.1 | Electrical installation test documentation | Self-built house |
| A new or altered electrical installation at building acceptance | LBN 261-15, points 53–55 | A protocol with documents, including approved reports on the measurements in sub-point 53.4 | Test protocol |
| Periodic inspection | Regulation No. 238, points 56 and 57 (in force until 1 January 2027) | Test report following Annex 6 | Periodic testing |
| Reconnection after a long break | Sadales tīkls recommendation | A check of the internal electrical installation before applying | Reconnection |
| Buying a house or flat | As needed by you or the parties to the transaction | An installation report or measurement report can be useful | Before buying a house |
The Sadales tīkls confirmation that the customer submits on e-st.lv about the readiness of the installation is a different document from a measurement protocol. There is a separate page about it, Sadales tīkls confirmation.
Checked on 25 November 2026: LBN 261-15 (likumi.lv/ta/id/274674), Cabinet Regulation No. 529 (likumi.lv/ta/id/269164), Regulation No. 238 (likumi.lv/ta/id/281646, in force until 1 January 2027).
Who may carry out measurements and who signs
Point 55 of LBN 261-15 states that the tests in sub-point 53.4 (wire and cable resistance, phase-neutral loop, earthing and the connection between earth electrodes) are carried out by a certified electrical specialist certified by an accredited body in line with LVS EN ISO/IEC 17024. For the periodic inspection, Regulation No. 238 does not name a construction specialist’s certificate. However, the report in Annex 6 comes with a copy of the electrical safety group card of the person doing the work, a copy of the instrument’s calibration or verification certificate and the electrical installation diagram (points 1.1–1.3 of the notes to the annex).
The documents are prepared and signed by a certified electrical specialist. How to check any electrician’s certificate is explained on the page about a certified electrician for documents.
What electrical installation testing costs
- Electrical installation measurements and report for a flat: from €170
- Measurements and documentation for putting a private house into use: from €230
- Site visit: €40
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. For a single measurement, lightning protection, a thermal camera inspection and business premises we quote the price after the site visit, because it depends on the number of distribution boards and circuits and the floor area. All prices in one table are on the page electrical document prices.
How to request testing and what to write in the form
- Fill in the form Give the address, the type of property (flat, house, office), who is asking for the document and why, and whether there is an old diagram or an earlier report. If you can, attach a photo of the distribution board.
- We get in touch After you send the form, we contact you within 5 minutes and clarify which document is needed.
- Site visit The site visit is paid: €40. The electrician looks over the distribution board and installation on site.
- Documents and price After the site visit we tell you which measurements and documents are needed and quote the price.
If the measurements show faults, an electrician has to put them right first, and only then can the documents be prepared. For repairs and electrical installation work there are electrician services in Riga. We work in the towns of the Riga region in the same way as in Riga.
Sources
- LBN 261-15 Internal Electrical Installations of Buildings (Cabinet Regulation No. 294 of 9 June 2015) checked 25 November 2026
- Cabinet Regulation No. 529 “Building Construction Regulations”, points 157.7.1 and 168.1 checked 25 November 2026
- Cabinet Regulation No. 238 “Fire Safety Regulations”, points 56–58, in force until 1 January 2027 checked 25 November 2026
- Sadales tīkls: reconnection checked 25 November 2026
- Sadales tīkls: permanent connection and confirmation checked 25 November 2026