The fire safety regulations currently in force (Cabinet Regulation No. 238) require testing once every 10 years, and the construction standard before putting into use and after significant changes. In other cases testing can be useful for knowing the condition of the installation.
How often electrical installations have to be tested
Point 56 of Cabinet Regulation No. 238: electrical installations, including earthing and lightning protection devices, are tested once every 10 years. If the property has an explosive atmosphere, once every two years; if a chemically aggressive environment, once a year. Together with this, distribution board contacts are checked with a thermal camera (point 58).
Regulation No. 238 is in force until 1 January 2027 and ceases to have effect on 2 January 2027. The text of the new regulations had not yet been published on 25 November 2026, so the 10-year interval may change. How this test is carried out: periodic electrical installation testing.
Checked on 25 November 2026: Cabinet Regulation No. 238 (likumi.lv/ta/id/281646), LBN 261-15 (likumi.lv/ta/id/274674), Sadales tīkls “Reconnection” (sadalestikls.lv/lv/piesleguma-atjaunosana).
Situations where testing is required or recommended
| Situation | Basis | What to order |
|---|---|---|
| 10 years have passed since the last test | Regulation No. 238, point 56 (in force until 1 January 2027) | Periodic testing with the Annex 6 and 7 reports |
| New or altered installation before putting into use | LBN 261-15 points 52–55 | Measurements and documents for the acceptance statement |
| A self-built Group 2 house is being handed over | Regulation No. 529, points 157.7.1 and 168.1 | Documents for putting a house into use |
| Significant changes: new distribution board, rewiring | LBN 261-15 point 52 | Measurements after the changes |
| Reconnection after a long interruption | Sadales tīkls recommendation | Testing before applying |
| Buying or renting out a house or flat | According to your needs or those of the parties | Testing or a report can be useful |
When to test the wiring in a house after a long interruption
If a house has been without electricity for a long time, Sadales tīkls recommends choosing a certified electrician and testing the internal electrical installation before applying. If it is not fit for use, Sadales tīkls does not restore the connection.
There is no charge for reconnection if the application is submitted within 30 days after the previous user has ended the contract with the electricity supplier. Later you pay a connection fee of €34.76 (0.4 kV) and the capacity maintenance fee for the time since the contract ended, for no more than 24 months, according to the Sadales tīkls price list, checked on 25 November 2026. More: reconnection.
Before a new connection, a capacity increase or solar panels
For a new connection or a capacity increase, Sadales tīkls requires the customer’s installation to be prepared by a qualified electrical specialist or an electrical installation company, and the customer submits a readiness confirmation on e-st.lv. This is the moment when it is worth testing the existing installation too, because the load will grow after connection.
For solar panels and a battery up to 11.1 kW (three phases) or 3.7 kW (one phase), Sadales tīkls accepts the inverter settings protocol only from a specialist whose certificate covers generating equipment. It also requires such a specialist to carry out the installation and adjust the inverter. More: connecting a microgenerator.
Before buying or renting out
When buying a house or flat, electrical installation testing can be useful: you know the condition before the transaction and can judge whether you will need to invest in repairs. If a bank, insurer or seller asks for a document, ask which one exactly. There is a page on this, report before buying a house. When renting out a flat, a report can be useful as a recorded condition before the tenant moves in.
Signs that testing is needed: when not to wait for the deadline
Some signs mean an electrician is needed now, not according to the schedule:
- protective devices trip repeatedly for no visible reason;
- a socket, switch or distribution board is warm, has changed colour or smells of burning;
- walls, the distribution board or cables have been affected after a flood or fire;
- the house has old wiring without earthing and without residual current devices.
If anything is getting hot or burning, that is a repair matter: contact an electrician, for example electrician services in Riga. Testing and documents are the next step after the repair. There are separate pages for after flooding and after a fire.
How to prepare for electrical installation testing
- Find out who the document is for The building authority, periodic testing, Sadales tīkls or a buyer. This determines which measurements and which document are needed.
- Find the papers The previous report, a design or diagram, the documents the electrician handed over after a renovation.
- Photograph the distribution board A photo with the door open, and of the meter, to attach to the form.
- Provide access Keys to distribution boards, the basement, the attic and outbuildings. Arrange access to the stairwell board with the building manager.
- Plan for a power cut Circuits are switched off for some of the measurements. Save your computer work and think about the fridge, heating or server.
What the electrician needs during the visit: free access to the distribution board, the rooms with sockets and the earthing point, and a person who knows which circuits supply what.
How much testing costs
- Electrical installation measurements and report for a flat: from €170
- Measurements and documentation for putting a private house into use: from €230
- Site visit: €40
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. The site visit is paid: €40. After it we tell you which documents are needed and quote the price.
Sources
- Cabinet Regulation No. 238 Fire Safety Regulations, points 56–58, in force until 1 January 2027 checked 25 November 2026
- Latvian Construction Standard LBN 261-15 “Internal Electrical Installations of Buildings” (Cabinet Regulation No. 294 of 9 June 2015) checked 25 November 2026
- Cabinet Regulation No. 529 Building Construction Regulations, points 157.7.1 and 168.1 checked 25 November 2026
- Sadales tīkls: Reconnection checked 25 November 2026
- Sadales tīkls price list checked 25 November 2026
- Sadales tīkls: permanent connection and confirmation checked 25 November 2026
- Sadales tīkls: Connecting a microgenerator checked 25 November 2026
- General technical requirements, point 9: installation and inverter adjustment are carried out by a building specialist with a generation specialisation checked 25 November 2026
- Sadales tīkls: the electricity network may be built by a qualified electrical specialist or an electrical installation company checked 25 November 2026