We prepare this electrical part in Riga and the Riga region after a site visit. Below you will find which page matches your building and situation.
What the building authority asks for regarding the electrical installation
Point 52 of LBN 261-15 states that electrical equipment is tested before putting into use and also after significant changes. Point 53 lists what is attached to the acceptance statement if the relevant works have been done. These are a corrected set of drawings, equipment data sheets and material conformity declarations, concealed works acceptance records, reports on wire and cable resistance, phase-neutral loop and earthing measurements, switching diagrams and an operating description.
The phase-neutral loop measurement shows whether a circuit breaker will disconnect the circuit quickly enough in case of a fault. Insulation resistance is tested under point 54 before acceptance into use. Under point 55, these tests are carried out by a certified electrical specialist certified by a body accredited to standard LVS EN ISO/IEC 17024.
The Building Construction Regulations (Cabinet Regulation No. 529) specifically mention electrical installation test documentation for a Group 2 residential house built by its owner (points 157.7.1 and 168.1). In other cases, the building authority’s requirements follow from the type of process: explanatory note, construction notification or building permit.
Checked on 25 November 2026: LBN 261-15 points 52–55 (likumi.lv/ta/id/274674), Cabinet Regulation No. 529 points 157, 167 and 168 (likumi.lv/ta/id/269164).
Which page matches your situation
If you built the house yourself on your own plot of land, start with the page self-built house. There the building authority asks for electrical installation test documentation directly under a point of the regulations.
Smaller buildings have their own pages: putting a garden house into use and sauna, garage or outbuilding. For saunas and shower rooms, point 27 of LBN 261-15 sets special requirements.
If you are altering or renovating a building, see electrical installation documents after alteration. For a flat there is a separate page on documents for flat rewiring, and for an office or shop on putting commercial premises into use.
If another electrician installed the wiring and there are no papers, read electrical installation documents when someone else did the work. For an old house without documents, the page putting an old house into use will help.
For individual documents: as-built diagram, as-built documentation, concealed works records and electrical installation documents for the building authority and BIS.
Situations and documents in one table
| Situation | What usually has to be prepared for the electrical part | Rule |
|---|---|---|
| Self-built Group 2 residential house | Electrical installation test documentation: measurements, diagram | Regulation No. 529, 157.7.1, 168.1 |
| New or altered installation at building acceptance | Protocol with annexes under point 53, insulation test | LBN 261-15 points 53, 54 |
| Alteration or significant changes | Testing after the changes, updated diagram | LBN 261-15 point 52 |
| Works that will be covered up | Concealed works acceptance records before covering up | LBN 261-15 sub-point 53.3 |
| Office or shop premises | Measurements, diagrams, operating description | LBN 261-15 sub-points 53.4, 53.5, 53.6 |
Which document is needed for your property is decided by the building authority. After the site visit we tell you which of them can be prepared and what the price will be.
Prices for the electrical part
- Measurements and documentation for putting a private house into use: from €230
- Site visit: €40
- As-built diagram / distribution board diagram: price after the site visit
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. The price of an as-built diagram depends on the building’s area and number of floors, the number of distribution boards and circuits, whether there is an old diagram or design, and how many cable routes have to be traced on site. All prices are on the prices page.
What to write in the request form
- Address and type of building: residential house, garden house, sauna, office.
- Which process has been started at the building authority: explanatory note, construction notification or building permit, if you know it.
- Who installed the electrical installation and whether there is a design, a diagram or earlier reports.
- What the building authority has already asked for, if there is such a letter or a note in BIS.
- A photo of the distribution board.
After you send the form, we contact you within 5 minutes. The site visit is paid: €40.
Sources
- LBN 261-15 points 52–55, point 27 checked 25 November 2026
- Cabinet Regulation No. 529 Building Construction Regulations, points 157, 160, 167, 168, 171 checked 25 November 2026