Which ones exactly depends on the document the construction started with: an explanatory note, a construction notification or a building permit. In Riga and the Riga region we prepare the electrical part that is attached to your case.
In the BIS case: where electrical installation documents are attached
In the Construction Information System (BIS), each construction project has its own case. Point 5 of the Building Construction Regulations (Cabinet Regulation No. 529) states that each municipality’s building authority examines cases in its own territory. In Riga this is the City Development Department of Riga State City Municipality. In cases started after 31 December 2019, acceptance can be requested electronically in BIS.
| Process | Where the electrical documents are attached | Point |
|---|---|---|
| Explanatory note | To Part II of the explanatory note; the construction log and as-built records are attached if a log has to be kept | Regulation No. 529, point 157 |
| Construction notification | To the BIS confirmation of completion, with reports on the readiness of utility networks; for a new Group 1 residential building, auxiliary building or agricultural building also with an as-built survey plan and façade photos | Regulation No. 529, point 156.¹ |
| Building permit | To the acceptance documents, including equipment test protocols if they are required | Regulation No. 529, point 167 |
If the building authority has already left notes in the BIS case about missing documents, paste that text into the form. After the site visit we can then say which of the missing items concern the electrical part.
Checked on 25 November 2026: Cabinet Regulation No. 529 points 5, 157, 160, 167, 168, 171 (likumi.lv/ta/id/269164), LBN 261-15 point 53 (likumi.lv/ta/id/274674), Riga building acceptance service (riga.lv).
Explanatory note Part II: the electrical part
Point 157 of Cabinet Regulation No. 529 lists what is attached to Part II of the explanatory note. This covers reports on utility network readiness, as-built drawings if anything was changed, the construction log with as-built records (except in the cases in point 120, including an owner-built house), an as-built survey plan and a temporary energy performance certificate. If the owner built the house, sub-point 157.7.1 additionally requires electrical installation test documentation.
Within 10 working days the building authority checks that there is no unauthorised construction and makes a mark on completion of the works (point 160). For an owner-built house, see the page self-built house.
Electrician’s report for the building authority and the measurement protocol
The word “report” in this context comes from sub-point 53.4 of LBN 261-15: approved reports on wire and cable resistance testing, phase-neutral loop measurements, and the resistance of the earthing loop and bonds are attached to the acceptance statement. In essence these are measurement results with a conclusion that they meet the standards.
Under point 55, these tests are carried out by a certified electrical specialist. A report on utility network readiness is a different document: it is issued by the body that gave the technical conditions, for example Sadales tīkls. Ask the building authority whether in your case it is a separate paper or is generated in BIS.
Confirmation that the building is ready for use
With a building permit, the confirmation that the building is ready for use is approved in BIS by the construction initiator, the building contractor, the construction works manager, the construction supervisor and the author’s supervisor (Cabinet Regulation No. 529, point 167.¹). Once all the documents in points 167 and 168 are received, the building authority agrees an acceptance date with the construction initiator, no later than 10 working days from submission of the documents (point 171).
- Find out Which process the BIS case uses and what the building authority has already asked for.
- Apply In the form, write the address, the process and the status of the BIS case.
- Site visit and measurements After them, the documents are prepared and signed by a certified electrical specialist.
- BIS case The electrical documents are attached to the BIS case together with the other acceptance documents.
How much electrical documents for the building authority cost
- Measurements and documentation for putting a private house into use: from €230
- Site visit: €40
- As-built diagram / distribution board diagram: price after the site visit
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. We work in Riga, Mārupe, Ķekava and elsewhere in the Riga region.
Sources
- Cabinet Regulation No. 529, points 5, 157, 160, 167, 167.¹, 168, 171 checked 25 November 2026
- LBN 261-15 sub-point 53.4, points 54, 55 checked 25 November 2026
- Riga: building acceptance service, requests for BIS cases started after 31 December 2019 checked 25 November 2026