It is issued after a confirmation on e-st.lv, with an inverter settings protocol attached, signed by a specialist with a certificate for generating equipment. Installation is done by an installer; we test and prepare the papers in Riga and the Riga region.
What Sadales tīkls calls a microgenerator
A microgenerator is generating equipment of up to 16 A per phase: 3.7 kW on a single-phase or 11.1 kW on a three-phase connection. A battery also counts as generating equipment, and the total inverter capacity must stay within these limits. A larger system is a power station with a different process.
The inverter must be on the list of inverters approved by Sadales tīkls (standard LVS EN 50549-1). Sadales tīkls decides separately on an inverter that is not on the list, and this can take up to 5 working days longer.
Sadales tīkls accepts the protocol only from the holder of a BLEEA or LEB certificate with a specialisation in power stations or generating equipment. An electrical safety group card is not considered a certificate. Sadales tīkls requires that the installation and inverter set-up are also carried out by a construction specialist with a certificate for generating equipment.
Checked on 25 November 2026: Sadales tīkls, “Connecting a microgenerator” and “Certification requirements for installers of generating equipment” (sadalestikls.lv).
Which page suits your system
Connecting a microgenerator: a new system of up to 11.1 kW, all the steps from application to permission, including expansion.
Inverter settings protocol: what has to be confirmed in it, who may sign it and what to do if you change the inverter.
Solar panels installed, Sadales tīkls papers not in order: the system is already on the roof, but the installer did not have the required certificate or permission has not been received.
Connecting a battery: a battery or hybrid inverter for an existing or new system. Solar power station for a business: systems above 11.1 kW. For these Sadales tīkls requires a certificate in the regulated sphere, and a construction design in BIS if a new connection has to be set up or the load changed.
Steps up to permission for parallel operation
| Step | Who | Sadales tīkls deadline or fee |
|---|---|---|
| Application on e-st.lv | Owner | Reply within 3 working days if the inverter is on the approved list |
| Assessment invoice | Owner | €78.66, not refunded if the application is withdrawn |
| Installation | Installer | Within 9 months of approval, can be extended once by up to 6 months |
| Confirmation with protocol | The owner; a certified specialist signs the protocol | Permission within 3 working days of the documents |
| Settlement option | Owner | Chosen after permission |
According to the Sadales tīkls price list and the page “Connecting a microgenerator”, checked on 25 November 2026 (sadalestikls.lv). Sadales tīkls writes that the whole process can take 1–2 months.
The net billing system for solar panels
The old “net metering” has been closed to new participants since 1 May 2024. Existing participants can use it until 28 February 2029, but changes, for example, of the user, settlement option or connection, can end participation. It is worth checking this before an expansion or inverter change.
New producers have two options: the net billing system or selling electricity to a supplier. The net billing system also includes a universal service up to 50 kW: the purchase price is the Nord Pool Latvia price minus no more than €0.02/kWh, not lower than 0, with a contract of at least 6 months. Until there is a contract with a supplier, the electricity produced is accepted into the network without payment.
Checked on 25 November 2026: Sadales tīkls, “Settlement options for electricity producers” (sadalestikls.lv/lv/norekinu-veidi-elektribas-razotajiem).
Do panels need the building authority
That depends on whether the installation requires construction work, for example, strengthening load-bearing structures or new networks. Sadales tīkls recommends finding out the local municipality’s requirements in good time, so ask your building authority about your particular house. The panels are installed by an installer, for example, solar panel installation.
Price of papers for Sadales tīkls
- Solar panel / microgenerator paperwork for Sadales tīkls and inverter settings protocol: price after the site visit. The price depends on: the number and type of inverters (grid-tied, hybrid); whether the inverter is on the list approved by Sadales tīkls; whether the installer’s mistakes have to be corrected; the Sadales tīkls assessment fee of €78.66 (separate).
- Site visit: €40.
After the site visit we tell you which documents are needed and quote the price. Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate.
What to write in the form
- The address and the number of phases of the connection.
- The inverter manufacturer, model and capacity; the battery, if there is one.
- Whether an e-st.lv application has already been submitted and when it was approved.
- Who installed the system.
- A photo of the inverter nameplate.
Sources
- Connecting a microgenerator: limits, steps, €78.66, 3 working days, 9 months, annexes checked 25 November 2026
- Certification requirements for installers of generating equipment (BLEEA, LEB, electrical safety group) checked 25 November 2026
- Settlement options for electricity producers checked 25 November 2026
- Sadales tīkls price list checked 25 November 2026
- General technical requirements, point 9: installation and inverter set-up are carried out by a construction specialist with a generation specialisation checked 25 November 2026