Until there is permission for parallel operation, the system may be run only in a brief test mode. We test another installer’s system and, after the site visit, tell you what has to be corrected and what can be done with the documents.
The most common situations and what they mean
| Situation | What has to be done |
|---|---|
| The e-st.lv application has not been submitted | Submit the application and pay the €78.66 assessment; then the confirmation with annexes |
| The application is approved, but there is no confirmation | Prepare the inverter settings protocol and annexes; check whether the 9-month deadline has passed |
| The inverter is not on the approved list | Sadales tīkls decides separately; a laboratory certificate, specification and manual are needed |
| The inverter has been replaced with another | If the new one is on the list and the capacity is no greater, the new inverter’s protocol is attached; otherwise a new application |
According to the Sadales tīkls pages “Connecting a microgenerator” and “Certification requirements for installers of generating equipment” and the price list, checked on 25 November 2026 (sadalestikls.lv).
Solar panels without documents: what happens to the electricity produced
Without Sadales tīkls permission only a brief test run is allowed. After permission a settlement option has to be chosen; until there is a contract with a supplier, the electricity produced is accepted into the network without payment. The old net metering has been closed to new participants since 1 May 2024, so it is no longer available to a system that is not yet connected.
Off-grid systems not connected to the network do not need Sadales tīkls permission.
Sadales tīkls checks the submitted documents and may inspect the property on site. It may also ask for a calculation showing that the voltage rise up to the network boundary does not exceed 2 %, or 4.6 V. If the installer has not left such a calculation, it is worth preparing it before the confirmation.
Solar panel documents after installation: how the check goes
- What you already have You show the status of the e-st.lv application and the installer’s documents, if there are any.
- Site visit We compare the inverter with the application and the list, and check the circuit breaker of up to 16 A between the inverter and the meter, the phases and the protection settings.
- Mistakes found We tell you what does not meet the Sadales tīkls requirements. The correction is done by an installer, for example, solar panel installation.
- Protocol and annexes If the system complies and a certified building specialist installed it and set up the inverter, we prepare the annexes; you submit the confirmation on e-st.lv.
Sadales tīkls requires that the installation, the inverter set-up and the protocol are all done by a construction specialist with a certificate for generating equipment.
Legalising solar panels and the building authority
The Sadales tīkls permission concerns the connection to the network. Whether anything has to be submitted to the building authority depends on whether the installation required construction work, for example, strengthening load-bearing structures or new networks. Ask your building authority about your particular house; Sadales tīkls also recommends finding out the municipality’s requirements in good time.
What to prepare
- Access to the e-st.lv account or the application number.
- The inverter model, capacity and a photo of the nameplate.
- The installer’s invoice, diagram or contract, if there is one.
- Access to the inverter and distribution board.
How much does sorting out the papers cost
- Solar panel / microgenerator paperwork for Sadales tīkls and inverter settings protocol: price after the site visit. The price depends on: the number and type of inverters (grid-tied, hybrid); whether the inverter is on the list approved by Sadales tīkls; whether the installer’s mistakes have to be corrected; the Sadales tīkls assessment fee of €78.66 (separate).
- Site visit: €40.
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate.
Sources
- Connecting a microgenerator: limits, steps, €78.66, 3 working days, 9 months, annexes checked 25 November 2026
- Certification requirements for installers of generating equipment (BLEEA, LEB, electrical safety group) checked 25 November 2026
- General technical requirements for connecting a microgenerator checked 25 November 2026
- Settlement options for electricity producers checked 25 November 2026
- Sadales tīkls price list checked 25 November 2026
- 2 % voltage rise checked 25 November 2026