Its list describes the electrical part in detail: four measurement reports issued by a person with a certificate. Sadales tīkls needs its own papers if a business wants a solar power station on the roof. The two recipients need different papers, and they should not be confused.
The Ķekava Municipality list: which measurements have to be submitted
Ķekava has detached-house areas, newer residential projects, a local centre and commercial development along the main roads. For owners of detached houses building for their own needs without construction supervision, the Ķekava Municipality document list names the electrical part precisely, referring to sub-point 53.4 of LBN 261-15.
The list includes electrical installation test documentation issued by a person with a certificate in the relevant field, containing reports on:
- conductor and cable resistance testing;
- phase-neutral loop measurements;
- earthing loop resistance;
- bonding resistance between earth electrodes and the parts to be earthed.
All four are measured during one site visit and go into one protocol with a circuit table. In Ķekava Municipality documents are submitted only in BIS, so receive the protocol electronically. What this looks like in a case is described on the page electrical installation documents for the building authority.
Building yourself in one of the municipality’s villages: concealed works records in time
Ķekava’s main connections are the A7 (Via Baltica) and the Riga bypass, and the municipality has a wide network of villages. Whichever village the house is in, the building authority and list are the same. What differs is only how far the construction has progressed by the time you remember the papers.
Sub-point 53.3 of LBN 261-15 states that concealed works acceptance records on the installation of electrical equipment are attached to the acceptance statement, if such works have been carried out. Concealed works are cables in walls, floors or under plaster that are no longer visible after finishing. A concealed works record is not recreated once the work has been covered up; ask the building authority what it accepts instead.
Checked 25 November 2026: Latvian Construction Standard LBN 261-15 “Internal Electrical Installations of Buildings” (Cabinet Regulation No. 294 of 9 June 2015), sub-points 53.3 and 53.4, likumi.lv; Ķekava Municipality building authority list for putting a building into use.
- Cables laid Before plastering or plasterboard, the electrician inspects the routes and a concealed works record is drawn up.
- Distribution board assembled Circuits labelled, protective devices installed, diagram prepared.
- Connection A confirmation is submitted to Sadales tīkls, and after connection measurements with voltage are possible.
- Measurements and protocol All four reports on the list and residual current device testing.
- BIS The protocol, diagram and records are added to the case with the other documents.
More: electrical installation test documentation for a self-built house.
Production facility, shop or logistics premises: what to prepare for putting into use
Ķekava’s functions are a municipal centre, production and the food industry, retail, logistics and commuting to Riga. If a business alters premises under a building authority case, the electrical part is the same as for a house, only larger: measurements by distribution board, diagrams and concealed works records if cables are hidden. If the premises will have powerful three-phase equipment, attach a list of it: it shows whether the existing connection is sufficient.
In a food production facility or a warehouse with freezers, say which equipment must not be switched off so that the measurements can be planned in parts. If you rent the premises, agree with the owner in whose name the documents will be submitted to the building authority. More: putting commercial premises into use.
A solar station on a business roof: above 11.1 kW, a different route
Production and logistics buildings in Ķekava can have large roofs, and a business may want a station bigger than a microgenerator. Sadales tīkls defines a microgenerator as up to 11.1 kW on three phases. Above that it is a power station with a separate process: Sadales tīkls issues technical requirements and a contract, and a building design in BIS is needed if a new connection has to be installed or the load changed. If the station does not exceed 11.1 kW, the microgenerator route with an e-st.lv application and an inverter settings protocol suits the business.
For a power station above 11.1 kW, Sadales tīkls accepts only a regulated-sphere certificate “Elektroietaišu izbūves darbu vadīšana” (managing electrical installation construction works) or “Elektroietaišu izbūves darbu būvuzraudzība” (supervising electrical installation construction works) with a generating equipment specialisation. A State Environmental Service permit is needed only from 500 kW. A specialist with this certificate installs the station and signs the test documents; we do not mount the station, but we prepare the measurements and documents on the property side for the business building. The process is described on the page connecting a business solar power station.
What papers for a house and business in Ķekava cost
Measurements and documentation for putting a private house into use cost from €230. For business premises we state the price after the site visit: it is determined by the floor area, the number of distribution boards and circuits and whether a thermal camera inspection is needed. Solar station papers are priced after the site visit, depending on the number and type of inverters. The site visit is paid: €40.
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. The documents are prepared and signed by a certified electrical specialist.
Sources
- LBN 261-15, sub-points 53.3 and 53.4 checked 25 November 2026
- Ķekava Municipality list: four reports, person with a certificate; utility network readiness reports checked 25 November 2026
- Ķekava Municipality: documents submitted only in BIS checked 25 November 2026
- Power station above 11.1 kW: building design in BIS if a new connection or load change is needed; State Environmental Service permit from 500 kW checked 25 November 2026
- Certificate for a power station above 11.1 kW: regulated sphere with generation specialisation checked 25 November 2026
- General technical requirements, point 9: installation and inverter set-up by a construction specialist with a generation specialisation checked 25 November 2026