If the house is being put into use, the building authority may ask for test documentation. In other cases the owner or a buyer orders the test.
What is tested in a house and how it differs from a flat
In a house, the owner is responsible for the whole installation from the incoming supply to the last socket, so the test also includes what in a flat belongs to the building as a whole.
| Part | What is checked | Regulation |
|---|---|---|
| Incoming distribution board | Main protective device, number of phases, a 300–500 mA protective device on the main incoming supply or an alternative solution | LBN 261-15, points 8.3 and 28.² |
| Earthing | Loop resistance and connection to the parts to be earthed | LBN 261-15, sub-point 53.4 |
| Circuits | Insulation, phase-neutral loop, 30 mA devices for sockets and lighting | LBN 261-15, points 28.¹, 53.4, 54 |
| Outdoor sockets and lighting | 30 mA protection for sockets for outdoor equipment; outdoor lighting equipment is a location with special requirements | LBN 261-15, points 28.¹ and 27.9 |
Since 1 July 2025 the residual current device requirements (points 28.¹ and 28.²) have applied to new and altered installations; for an older installation the report records where there is no such device. Point 8.3 states that in a residential building a supply with a protective device larger than 32 A is connected only in three-phase form. If a capacity increase is planned for the house, mention it in the form before the test.
Checked on 25 November 2026: LBN 261-15 (likumi.lv/ta/id/274674), Cabinet Regulation No. 529 (likumi.lv/ta/id/269164), Regulation No. 238 (likumi.lv/ta/id/281646, in force until 1 January 2027).
Electrical installation testing in a sauna and garage
Point 27 of LBN 261-15 lists locations where there are special requirements for electrical installations. On a private house plot the most common are rooms with a bath or shower, places with sauna heaters and outdoor lighting equipment. So electrical installation testing in a sauna and shower room is a separate part of the house test.
A garage and an outbuilding usually receive power through a cable from the house distribution board. The test measures this cable’s insulation, the phase-neutral loop and the protective conductor connection, and checks whether the sockets have a residual current device. If the sauna, garage or outbuilding needs documents for putting into use, see the page sauna, garage and outbuilding.
When a house test is required and when it can be useful
- Required: for a Group 2 residential building that the owner has built personally (Construction Law, Section 19.¹, paragraph three), Cabinet Regulation No. 529, points 157.7.1 and 168.1, requires electrical installation test documentation for putting into use.
- Required: the periodic inspection once every 10 years under the fire safety regulations currently in force (Cabinet Regulation No. 238); the regulations are in force until 1 January 2027.
- Recommended: before reconnection after a long break, Sadales tīkls recommends having the installation checked.
- Can be useful: before buying a house or if an old installation comes to light.
Putting a self-built house into use has its own page, self-built house, because besides measurements a diagram and other documents under point 53 of LBN 261-15 may be needed there.
How to prepare the house for testing
- List Write in the form which buildings on the plot are connected: house, sauna, garage, shed, greenhouse.
- Documents Get ready the existing design or diagram, earlier reports and, if the house is new, the papers handed over by the electrician.
- Access Provide access to all distribution boards, the earthing point and the buildings. During the test the circuits will be switched off for a while.
- Photos Attach a photo of the incoming distribution board and the meter; it helps to estimate the scope before the site visit.
What electrical installation testing in a house costs
- Measurements and documentation for putting a private house into use: from €230
- Site visit: €40
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. For a house the price is affected by the floor area, the number of distribution boards and circuits, how many buildings are connected and whether there is earlier documentation.
Sources
- LBN 261-15 Internal Electrical Installations of Buildings (Cabinet Regulation No. 294 of 9 June 2015) checked 25 November 2026
- Cabinet Regulation No. 529 “Building Construction Regulations”, points 157.7.1 and 168.1 checked 25 November 2026
- Construction Law, Section 19.¹, paragraph three checked 25 November 2026
- Cabinet Regulation No. 238 “Fire Safety Regulations”, points 56–58, in force until 1 January 2027 checked 25 November 2026
- Sadales tīkls: reconnection checked 25 November 2026