It is attached to the documents for putting into use, test reports are based on it, and it helps the next electrician find the right circuit. We prepare as-built diagrams for houses, flats and commercial premises in Riga and the Riga region.
Where the regulations require an electrical installation diagram
“As-built diagram” is a trade term; the regulations use other names. For acceptance of a building into use, point 53 of LBN 261-15 requires further documents to be attached if the relevant works have been done. They include a set of drawings corrected as part of author’s supervision (53.1) and the installation’s automatic control and electrical switching diagrams (53.5).
The test report in Annex 6 of the fire safety regulations currently in force (Cabinet Regulation No. 238) has an electrical installation diagram attached. It shows the nominal values of the protective devices and the types and cross-sections of the outgoing cables or wires (point 1.3 of the notes to the annex). So the diagram is also useful for the periodic test once every 10 years. Regulation No. 238 is in force until 1 January 2027.
Checked on 25 November 2026: LBN 261-15 points 53.1 and 53.5 (likumi.lv/ta/id/274674), Cabinet Regulation No. 238 points 56–57 and Annex 6 (likumi.lv/ta/id/281646).
Distribution board diagram and single-line diagram
A distribution board diagram shows what is in the board: the main protective device, residual current devices (RCDs), circuit breakers and which rooms or equipment each breaker supplies. A copy of this diagram fixed to the board door lets you switch off the right circuit quickly.
In a single-line diagram, all the conductors of one circuit are drawn as one line. It is compact and shows the structure of the installation from the incoming supply to the circuits: cable cross-sections, nominal values of the protective devices and circuit names.
| Type of diagram | What it shows | Where it is useful |
|---|---|---|
| Distribution board diagram | Devices in the board and circuit names | At the board, in daily use and during repairs |
| Single-line diagram | Incoming supply, protective devices, cables, circuits | For putting into use and for test reports |
| Room plan with cable routes | Where the cables run in the walls | After alteration, before a renovation |
Flat wiring diagram
In a flat the diagram usually starts at the flat’s distribution board and covers all its circuits. A flat wiring diagram is needed after alteration, can be useful when selling or renting out the flat, and helps to link each result in the test report to a specific circuit.
If the whole installation in the flat has been replaced, see also the page documents for flat rewiring.
How an as-built diagram is made on site
- Distribution board Each device, its nominal value and type are written down.
- Circuits The breakers are switched off in turn to establish which sockets, light fittings and equipment are connected to them.
- Routes If a room plan is needed, cable routes are traced where they can be determined without opening the walls.
- Comparison If there is a design or an old diagram, the differences are noted.
- Drawing up The diagram is drawn up and attached to the measurement documents or handed over separately.
In the form, attach a photo of the distribution board with the door open and, if there is one, the old diagram or design. While the circuits are being identified, the electricity will go off briefly in individual rooms.
It is worth keeping two copies of the finished diagram: one by the distribution board and the other with the building documents. If anything in the installation is changed later, the diagram is updated so that it matches what was built again.
How much an as-built diagram costs
- As-built diagram / distribution board diagram: price after the site visit
- Site visit: €40
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. The price of an as-built diagram depends on the building’s area and number of floors, the number of distribution boards and circuits, whether there is an old diagram or design and how many cable routes have to be traced on site. For a private house, measurements and documentation for putting into use cost from €230.
Sources
- LBN 261-15 points 53.1 and 53.5 checked 25 November 2026
- Cabinet Regulation No. 238 points 56–57 and Annex 6, in force until 1 January 2027 checked 25 November 2026
- Cabinet Regulation No. 169: certificate in the design of electrical installations (8.5) checked 25 November 2026