Before ordering, find out who is asking for the document, because that determines the content and who may sign. Below are the document names as written in the sources.
Who asks for which document
| Document (name in the source) | Regulation | When it is needed |
|---|---|---|
| A protocol with documents attached to the acceptance statement, including “approved reports” on wire and cable resistance, the phase-neutral loop and earthing | LBN 261-15, point 53 | Accepting a building into use |
| Electrical installation test documentation | Cabinet Regulation No. 529, points 157.7.1 and 168.1 | Putting a self-built Group 2 residential building into use |
| Test report on the electrical installation’s insulation resistance, total impedance of the phase-neutral loop, earthing installation resistance, earthing conductor continuity and lightning protection system | Regulation No. 238, point 57 and Annex 6 | Periodic inspection (regulations in force until 1 January 2027) |
| Test report on electrical installation contact connections | Regulation No. 238, point 58 and Annex 7 | Together with the periodic inspection |
| Inverter settings protocol | Sadales tīkls requirements for a microgenerator | Connecting solar panels or a battery |
Checked on 25 November 2026: LBN 261-15 (likumi.lv/ta/id/274674), Cabinet Regulation No. 529 (likumi.lv/ta/id/269164), Regulation No. 238 (likumi.lv/ta/id/281646), Sadales tīkls “Connecting a microgenerator” (sadalestikls.lv/lv/mikrogeneratora-pieslegsana).
Electrical installation measurement protocol for the building authority
When a building is accepted into use, point 53 of LBN 261-15 requires a protocol with documents to be attached to the acceptance statement, if the relevant works have been carried out. These are corrected drawings, equipment passports, concealed works records, measurement reports, switching diagrams, an operating description and training records. The electrician’s measurements are in sub-point 53.4, and they are carried out by a certified electrical specialist (point 55).
Point 54 requires insulation resistance to be tested before acceptance. If a diagram is also needed, it is separate work: as-built diagram.
Electrical installation test report for the periodic inspection
In the fire safety regulations currently in force (Cabinet Regulation No. 238), the report form is given in Annex 6. The form has fields for each type of measurement, the instrument data and its calibration certificate number. The report is signed by the person who did the work. Regulation No. 238 does not name a construction specialist’s certificate for them. However, the report in Annex 6 comes with a copy of the electrical safety group card of the person doing the work, a copy of the instrument’s calibration or verification certificate and the electrical installation diagram (points 1.1–1.3 of the notes to the annex).
Together with it, the Annex 7 report on the thermal camera inspection of contact connections is prepared. A measurement report drawn up after 19 April 2016 is valid until the next inspection (Regulation No. 238, point 525), so keep both reports.
The confirmation for Sadales tīkls is not a measurement protocol
For a new connection or a capacity increase, Sadales tīkls requires a confirmation on e-st.lv that the customer’s electrical installation has been built and is ready. Point 99 of Cabinet Regulation No. 635 calls it a written confirmation that the electrical installation is ready to be energised. That is a different document from a measurement protocol. If Sadales tīkls asks for an attachment in your case, ask which one exactly. More: confirmation for Sadales tīkls.
An electrician’s test report: what it should show
Whatever the name, check that the document contains these things. Without them the report is hard to use at the building authority or at the next inspection.
- the property address and the date of the test;
- which distribution boards and circuits were tested;
- the type of each measurement, the measured value and the comparison with the standard;
- the measuring instrument and its calibration certificate number (in Annex 6 of Regulation No. 238 this is a field on the form);
- the name and signature of the person who did the work, and for building acceptance also the certificate data.
Construction practice certificates are checked in the BIS register of construction specialists, while BLEEA and LEB certificates are checked using the issuer’s data and the four Sadales tīkls criteria. How to do this is explained on the page how to check an electrician’s certificate.
What to prepare so that the electrician can draw up the report
- Who is asking for the document and in what form: building authority, property manager, tenant, buyer.
- The existing diagram or design, earlier reports.
- Access to all distribution boards and rooms.
- If another electrician installed the wiring, the papers they handed over.
The documents are prepared and signed by a certified electrical specialist after a site visit and measurements. We do not sign a report without testing on site.
What an electrical installation report costs
- Electrical installation measurements and report for a flat: from €170
- Measurements and documentation for putting a private house into use: from €230
- Site visit: €40
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate.
Sources
- LBN 261-15 Internal Electrical Installations of Buildings (Cabinet Regulation No. 294 of 9 June 2015) checked 25 November 2026
- Cabinet Regulation No. 529 “Building Construction Regulations”, points 157.7.1 and 168.1 checked 25 November 2026
- Cabinet Regulation No. 238 “Fire Safety Regulations”, points 56–58, in force until 1 January 2027 checked 25 November 2026
- Cabinet Regulation No. 635 “Electricity Trade and Use Regulations”, points 44 and 99 checked 25 November 2026
- Sadales tīkls: permanent connection and confirmation checked 25 November 2026
- Sadales tīkls: connecting a microgenerator checked 25 November 2026
- Sadales tīkls: where to find a good electrician (BIS register) checked 25 November 2026