It is ordered by the property manager or the flat owners’ association. The internal installation of each flat is the responsibility of its owner.
What is tested in the shared part of the building
| Location | Measurements and testing |
|---|---|
| Incoming distribution board | Insulation, phase-neutral loop, earthing conductor connection, thermal camera |
| Stairwell distribution boards | Condition of connections with a thermal camera, line insulation, protective devices |
| Common-area lighting, cellar, loft | Insulation and phase-neutral loop for each circuit |
| Earthing installation | Earthing installation resistance and connection |
| Lightning protection | System test, if the building has one installed |
This list mainly matches the measurements listed in point 57 of Regulation No. 238 and the thermal camera inspection in point 58. The protective devices are also inspected. The results go into two reports: in Annexes 6 and 7.
Checked on 25 November 2026: Cabinet Regulation No. 238 “Fire Safety Regulations”, points 56–58 (likumi.lv/ta/id/281646), in force until 1 January 2027; Sadales tīkls “Load changes” (sadalestikls.lv/lv/slodzes-izmainas).
Stairwell distribution board testing
If the stairwell boards hold the flat meters and the protection of the flat supplies, the load of the whole floor flows through them. A thermal camera inspection is particularly useful here, because a loose connection heats up under load. That is why a time when the flats are drawing load is chosen for the thermal camera inspection; we arrange it after the site visit.
The meters and seals belong to Sadales tīkls. Sealed parts are not opened without permission from Sadales tīkls.
Electrical installation testing for a property manager: deadlines and documents
The fire safety regulations currently in force (Cabinet Regulation No. 238) set an inspection once every 10 years regardless of the form of ownership of the property. The regulations are in force until 1 January 2027, and the text of the new regulations had not yet been published on 25 November 2026. A property manager does well to keep both reports with the building documents, so that next time it can be seen what has been tested.
If a flat owner wants to increase capacity, Sadales tīkls requires the property manager’s written consent. That is a moment when a property manager does well to know the condition of the incoming and stairwell distribution boards.
After renovation or electrical installation alterations
If the risers, stairwell boards or incoming supply in the building have been replaced, it is no longer just a periodic inspection. Point 52 of LBN 261-15 requires testing before putting into use and after significant changes, and point 53 sets the documents attached to the acceptance statement. More about this: alteration and renovation.
How the testing goes
- Request The building address, number of stairwells and floors, whether there is lightning protection, the year of the previous report.
- Site visit A visit to the property costs €40. The electrician looks at the incoming and stairwell distribution boards.
- Notice to residents For some measurements the common-area circuits are switched off. The property manager warns residents in advance.
- Measurements and reports After the measurements, the reports in Annexes 6 and 7 are prepared. An electrician puts the shortcomings right, for example electrical installation repairs in Riga.
What to prepare
- Keys to the incoming distribution board room, stairwell boards, cellar and loft.
- The building’s electrical installation diagram or design, if it has survived.
- Earlier test reports.
- A contact person who can accompany the electrician around the building.
- A list of common equipment that must not be switched off without warning, for example the lift, heating substation or door system.
Flat owners can order electrical installation testing in a flat separately for their own flat.
What apartment building electrical installation testing costs
Measurements and documents for apartment buildings: price after the site visit. It is affected by the floor area, the number of distribution boards and circuits, lightning protection and the scope of the thermal camera inspection.
- Site visit: €40
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate.
Sources
- Cabinet Regulation No. 238 “Fire Safety Regulations”, points 56–58, in force until 1 January 2027 checked 25 November 2026
- Sadales tīkls: load changes checked 25 November 2026
- LBN 261-15 Internal Electrical Installations of Buildings (Cabinet Regulation No. 294 of 9 June 2015) checked 25 November 2026