The report shows the technical condition: what conductors and protective devices there are, whether there is earthing and which circuits should be replaced first. That way you plan repairs on facts rather than guesses.
What the site visit shows in an old electrical installation
| What is found | What it means for the owner |
|---|---|
| Fuses or old circuit breakers | When planning new circuits or a larger load, you have to expect the distribution board to be replaced |
| No residual current device (RCD) | When altering, the current LBN 261-15 requirements have to be followed, see below |
| Two-wire installation without an earth conductor | The sockets have no protective earthing |
| Aluminium conductors | The report states which circuits they are in, and measurements show the condition of the insulation |
| Extension leads and circuits added later | The diagram, if there is one, no longer matches what is there |
If figures are needed, measurements are added to the site visit: insulation resistance, phase-neutral loop and earthing. They show whether the circuits can be used until repairs.
Aluminium wiring
Aluminium conductors are found in older buildings. The report states which circuits they are in and what condition the connections in the distribution board and visible boxes are in. If the condition of the connections raises questions, the board and boxes can be checked with a thermal camera, see thermal camera inspection of a distribution cabinet. Whether to replace the aluminium circuits at once or gradually is the owner’s decision after the report.
If you rewire: requirements since 1 July 2025
- Residual current protection of no more than 30 mA for general sockets up to 32 A, outdoor sockets up to 32 A and lighting circuits in households (LBN 261-15 point 28.¹).
- In the main incoming distribution board of a single-family house, residual current protection of 300–500 mA on the main incoming supply, or an alternative technical solution (point 28.²).
- In residential buildings, a main protective device above 32 A is connected only in a three-phase arrangement (point 8.3).
LBN 261-15 (Cabinet Regulation No. 294) points 8.3, 28.¹ and 28.², as worded by Cabinet Regulation No. 355 of 17 June 2025, likumi.lv. Checked on 25 November 2026.
The alteration is done by an electrician, for example, electrical installation replacement and repairs in Riga. After the alteration we prepare the measurements and documents: see electrical installation documents after alteration.
An inherited or long-unoccupied house
If the electricity supply was interrupted for a long time, Sadales tīkls recommends choosing a certified electrician and checking the internal electrical installation before reconnection; if it is not fit for use, the connection cannot be restored. No fee is paid for reconnection only if it is requested within 30 days after the previous user’s contract ended. Later you pay for the connection (€34.76 in the 0.4 kV network according to the Sadales tīkls price list, checked on 25 November 2026) and the capacity maintenance fee for up to 24 months. More: restoring an electricity connection.
Sadales tīkls, sadalestikls.lv/lv/piesleguma-atjaunosana and /lv/cenradis. Checked on 25 November 2026.
What to prepare
- The address, type of building and approximate age of the electrical installation, if you know it.
- Old diagrams, a design or earlier test reports, if they have survived.
- Photos of the distribution board and meter.
- Whether the property currently has electricity.
- What you are planning: to live as it is, renovate in stages or replace everything.
How much does an old electrical installation site visit cost?
- Electrical installation report: from €180
- Site visit: €40
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. The price changes with the floor area, the number of distribution boards and circuits, whether there is an old diagram and whether measurements are needed. Other prices: prices.
Sources
- LBN 261-15 points 8.3, 28.¹, 28.², Cabinet Regulation No. 355/2025 checked 25 November 2026
- Regulation No. 238, points 54 and 56, in force until 1 January 2027 checked 25 November 2026
- Reconnection: 30 days, testing recommended, up to 24 months checked 25 November 2026
- Connection €34.76 checked 25 November 2026