LBN 261-15 sets special requirements for the electrical installation of a building site. We check the site distribution board and installation, and later prepare the papers for the permanent connection and for putting the house into use.
Temporary Sadales tīkls connection: the rules
| Type | Period | Condition | Fee according to the price list |
|---|---|---|---|
| Temporary connection for a building site | Up to 24 months | A valid building permit | €117.21, or €217.52 with additional installation work |
| Short connection for an event | Up to 31 days | Request 10 working days in advance | According to the price list |
According to the Sadales tīkls price list (the row on setting up a temporary connection for a building site) and the page “Temporary connection”, checked on 25 November 2026 (sadalestikls.lv).
Building site electricity connection: why it is different
Point 27 of LBN 261-15 lists places where special requirements according to standards apply to electrical installations, and one of them is construction sites (sub-point 27.4). On a building site the cables are outdoors, equipment is moved around and many people work with it. So the condition and protection of the site distribution board have to be checked before work begins.
For outdoor sockets up to 32 A used to connect portable equipment, point 28.¹ of LBN 261-15 requires a residual current device (RCD) with a rated operating current of no more than 30 mA.
Checked on 25 November 2026: LBN 261-15 sub-point 27.4 and point 28.¹, likumi.lv/ta/id/274674.
From a temporary to a permanent connection
The temporary connection ends, but the house needs a permanent one. Its steps are described on the page new Sadales tīkls connection: application, construction, your installation and the confirmation on e-st.lv. Request it in good time, because a permanent connection has its own steps and Sadales tīkls deadlines.
When the house is put into use, the documents under point 53 of LBN 261-15 are attached for the building authority, if the relevant work has been done. If the installation is covered by finishing, the concealed works records must be drawn up before it is covered, because they cannot be drawn up later. More: concealed works records.
If you build the house yourself as the builder (Construction Law Section 19.¹, paragraph three), the Building Construction Regulations (Regulation No. 529) require “electrical installation test documentation” for putting it into use (sub-points 157.7.1 and 168.1). More on this: self-built house.
Temporary power supply for construction: how it goes
- Building permit Make sure the building permit is valid; without it the temporary connection is not granted.
- Application on e-st.lv You request the temporary connection and the capacity needed.
- Site distribution board An installer or electrician installs the distribution board; we check it.
- Application for the permanent connection Request it in good time, before the temporary connection period ends.
What to prepare
- The building permit and its validity period.
- The capacity needed: cranes, concrete mixers, heaters.
- The place where the site distribution board will stand.
- If there is one: the design of the house’s electrical installation.
How much does a site distribution board check cost
- Documents and electrician’s work for Sadales tīkls: price after the site visit. The price depends on: whether the incoming supply and distribution board already suit the new capacity; whether you need to change the main protective device or switch to 3 phases; whether measurements are needed; Sadales tīkls fees according to its price list (separate).
- Site visit: €40.
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate.
Sources
- Temporary connection: 24 months, building permit, 31 days, 10 working days checked 25 November 2026
- Sadales tīkls price list checked 25 November 2026
- Latvian Construction Standard LBN 261-15 “Internal Electrical Installations of Buildings” (Cabinet Regulation No. 294 of 9 June 2015) checked 25 November 2026
- Cabinet Regulation No. 529 of 2 September 2014 “Building Construction Regulations” checked 25 November 2026