The building authority, in Riga the City Development Department, asks for electrical installation test documentation when putting the building into use if the owner built the house themselves. Sadales tīkls asks, for a new connection, for a confirmation on e-st.lv that the installation on your side is ready. If there will be solar panels on the roof, a third paper is added: the inverter settings protocol.
A house you built yourself: electrical papers for putting it into use
The typical buildings of Berģi are detached houses, newer private house projects, low-rise buildings and roadside commercial properties. If you are building the new house yourself, one legal provision matters. Section 19.1, paragraph three of the Construction Law allows an owner to build a house of up to 400 m² on their own land, acting as the builder. For such a second-group residential house, the Building Construction Regulations require electrical installation test documentation at acceptance.
In practice this means measurements (insulation, phase-neutral loop, earthing, residual current devices), a report with the results and an electrical installation diagram. Under LBN 261-15, the measurements are carried out by a certified electrical specialist. In Riga, for construction cases opened after 31 December 2019, acceptance can be requested in BIS, and the documents are added to the case there. Arrange the measurements while the board and circuits are still accessible, not the day before applying. Read all about this case on the page electrical installation test documentation for a self-built house.
Checked 25 November 2026: Construction Law, Section 19.1, paragraph three (likumi.lv/ta/id/258572); Building Construction Regulations, sub-points 157.7.1 and 168.1 (likumi.lv/ta/id/269164).
A new connection towards Brīvības gatve: the steps on your side
Berģi is reached via Brīvības gatve and the A2 direction, and in a new project the plot may not yet have an address at first. In that case give the cadastral designation and the nearest junction in your request to Sadales tīkls and to us, so the property can be found. For a permanent connection the Sadales tīkls procedure is this:
- Application on e-st.lv If the network does not need rebuilding, Sadales tīkls offers the final costs and a contract within 3 days; if it does, it issues technical requirements.
- Installation up to the Sadales tīkls distribution cabinet A qualified electrical specialist or electrical installation company installs the cable to the cabinet and the indoor installation.
- Confirmation You submit a confirmation on e-st.lv that the installation is ready. The capacity maintenance fee starts from this moment.
- Meter Sadales tīkls gets in touch within 2 working days to install the meter.
The confirmation and the measurement protocol are different documents: you submit the confirmation to Sadales tīkls, while the measurement report is added to the building authority documents. More detail: Sadales tīkls new connection.
Solar panels on the roof of a new house
Berģi is a green eastern suburban neighbourhood near Brīvības gatve and the area around Lake Jugla, with detached houses and private roofs. If solar panels of up to 11.1 kW on a three-phase connection (3.7 kW single-phase) are planned for the house, it is a microgenerator connection with its own Sadales tīkls procedure. The application is assessed for €78.66 under the Sadales tīkls price list, checked 25 November 2026. If you plan panels later, mention it already in the connection request: on a single-phase connection the microgenerator limit is 3.7 kW, on a three-phase connection 11.1 kW.
The inverter settings protocol is signed by a specialist whose certificate covers generating equipment. On 23 March 2022 the Riga municipality explained that no building authority permit is needed to install panels if no construction work, such as reinforcing load-bearing structures, is required. The installer who mounts the panels and sets up the inverter must hold the same kind of certificate. We do not do the mounting, but we check the result and draw up the papers. The steps are described on the page connecting a microgenerator.
As-built diagram: when the building authority also benefits from a drawing
An as-built diagram is an electrical installation diagram that shows how the installation was actually built: incoming supply, distribution boards, protective devices and circuits. Berģi serves housing, roadside commerce, education and suburban services, so one plot may have a house and a small commercial building with a shared incoming supply. The diagram then has to show which board feeds which building.
For acceptance of a building, LBN 261-15, point 53, lists both drawings and switching diagrams and reports on measurements as separate attachments, if the work concerned has been carried out. A measurement report shows the values, but only the diagram lets the examiner understand which circuit they belong to. If the design diagram was changed during construction, the as-built diagram is drawn from the actual state. More on this: as-built diagram for electrics.
What papers for a new house cost in Berģi
Measurements and documentation for putting a private house into use cost from €230. For Sadales tīkls documents and solar panel papers we give the price after the site visit. It is affected by whether the incoming supply and board already match the requested capacity, the number and type of inverters and whether the inverter is on the Sadales tīkls list of recognised inverters. The site visit costs €40. Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate.
Other neighbourhoods on this side: measurements and documents in Jugla, garden and new house documents in Bukulti, papers for low-rise houses in Brekši and electrical documents in Suži. All of Riga: neighbourhoods; the Riga region: list of places.
Sources
- Construction Law, Section 19.1, paragraph three: the owner builds a house of up to 400 m² checked 25 November 2026
- Building Construction Regulations, sub-points 157.7.1 and 168.1: electrical installation test documentation checked 25 November 2026
- LBN 261-15, points 53 and 55 checked 25 November 2026
- New connection steps, confirmation, 2 working days for the meter checked 25 November 2026
- Microgenerator up to 11.1 kW, assessment €78.66 checked 25 November 2026
- Riga municipality, 23 March 2022, on solar panels without construction work checked 25 November 2026
- In Riga, cases after 31 December 2019 in BIS checked 25 November 2026
- Sadales tīkls: customer installation is done by a qualified electrical specialist or electrical installation company checked 25 November 2026
- General technical requirements, point 9: installation and inverter set-up are carried out by a construction specialist with a generation specialisation checked 25 November 2026