A commercial property near the airport and the Mārupe roads may need measurements, an as-built diagram and documents that go into the building authority case with the rest of the set for putting into use.
Putting a self-built house into use: what to write in your request
The typical buildings of Beberbeķi are detached houses, gardens, forest areas and a few commercial properties. If the owner built a second-group residential house themselves, the Building Construction Regulations (points 157.7.1 and 168.1) require electrical installation test documentation for acceptance. In Riga, for cases opened after 31 December 2019, the application for acceptance can be submitted in BIS, and the municipality’s City Development Department carries out the acceptance.
So that the measurements can be planned in one visit, write in your request:
- whether the house already has a case in BIS and at what stage it is;
- how many distribution boards there are and whether any outbuildings have electricity;
- whether you installed the electrics yourself or someone else did;
- whether there is a design diagram and whether what was built differs from it.
Beberbeķi has forest, the nearby airport and a sparser street network. If the house stands at the forest edge far from the street, the supply cable from the Sadales tīkls distribution cabinet to the house may be long, and it is part of your installation. It is measured together with the house circuits, and the diagram shows its length and protection.
For the full list of documents in this case, see the page electrical documents for a self-built house.
A commercial property near the airport: the electrical part of the set for putting into use
Beberbeķi serves housing, logistics, services connected with the nearby airport and land management. If you are building or rebuilding a warehouse, a service building or an office, the set for putting it into use is wider than for a house. The Riga municipality’s document list for putting into use also includes acceptance records for significant structures and concealed works, the construction log and a statement on the readiness of the utility connection.
The electrical part of this set is the measurements, the as-built diagrams and the concealed works records on the installation of electrical equipment, which are drawn up during the work, not after it. If a site manager runs the project, agree with them when the installation will be ready for measurements. For how commercial premises are put into use, see the page putting commercial premises into use.
If concealed works records on the electrical installation were not drawn up while the cables were still visible, they are not recreated after covering up; ask the building authority what it accepts instead. So for a commercial property, arrange the electrician’s visit before ceilings and walls are closed up.
Panels installed, no papers: when the inverter is not on the list
Detached houses at the forest edge may have solar panels that someone else installed while the papers for Sadales tīkls were left unfinished. The first thing to check is the inverter. Sadales tīkls accepts inverters from its list of recognised inverters that comply with the standard LVS EN 50549-1. Sadales tīkls decides on an unlisted inverter separately, and that can take up to 5 working days more.
| What is missing | What to do |
|---|---|
| The inverter is not on the list | Submit the inverter’s laboratory certificate, specification and manual to Sadales tīkls for assessment |
| No inverter settings protocol | If a certified specialist did the installation and set-up, the protocol is drawn up and signed by a holder of a generation-field certificate |
| No confirmation on e-st.lv | Submit the confirmation with the protocol and photos of the data plate and equipment |
| The installer cannot be reached | Find out their certificate and its validity |
Checked 25 November 2026: Sadales tīkls, “Connecting a microgenerator”; list of recognised inverters (LVS EN 50549-1), unlisted ones are assessed separately, up to 5 working days more.
Sadales tīkls requires that the panels are mounted, the inverter set up and the protocol signed by a holder of a generation certificate. We do not install panels; after the site visit we tell you what can be done with the documents. More on this: panels installed by someone else, papers not in order.
Once Sadales tīkls has received the confirmation with all attachments, it issues permission for parallel operation within 3 working days. Until then the system may run only in a short test mode.
A warehouse with an office: one diagram or two
In a commercial property near Kārļa Ulmaņa gatve, the warehouse part and the office may share an incoming supply but have separate distribution boards. The as-built diagram (an electrical installation diagram showing what was actually built) can be one for the whole property, with each board shown on its own sheet. If the office is let to another user, they benefit from their own diagram sheet with their circuits and protection.
The scope of the diagram depends on the number of distribution boards and circuits and on how many cable routes have to be traced on site. If there is a design, attach it, and then only the differences are checked. For how the diagram is prepared, see the page as-built diagram.
Prices for a house, a commercial property and panel papers
Measurements and documentation for putting a private house into use cost from €230. For measurements and documents for a commercial property or warehouse the price is set after the site visit, because it depends on the floor area and the number of distribution boards and circuits. For panel papers for Sadales tīkls the price is set after the site visit: what matters is whether the inverter is on the recognised list and whether the installer’s errors have to be fixed. The site visit is paid: €40.
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. The documents are prepared and signed by a certified electrical specialist.
Sources
- Building Construction Regulations, points 157.7.1 and 168.1: electrical installation test documentation for a self-built house checked 25 November 2026
- Riga municipality document list for acceptance; cases in BIS after 31 December 2019 checked 25 November 2026
- List of recognised inverters (LVS EN 50549-1); unlisted ones assessed separately, up to 5 working days more; attachments to the confirmation checked 25 November 2026
- General technical requirements, point 9: installation and inverter set-up are carried out by a construction specialist with a generation specialisation checked 25 November 2026