For a new connection Sadales tīkls expects a confirmation on e-st.lv that the internal installation is ready. For putting a self-built house into use the building authority requires electrical installation test documentation. For a sauna, garage or shed perhaps no one asks for papers, but measurements show whether the line to them is safe.
New connection for a plot: what you must do and what Sadales tīkls does
Trīsciems is made up of detached houses, gardens, low-rise buildings and large natural areas, and if your plot has no electricity yet, the first step is a connection. A new connection is a job for two parties. Sadales tīkls builds the network up to its distribution cabinet and installs the meter. Everything beyond the boundary, that is, the cable to your distribution board and the internal installation, is the customer’s part, prepared by an electrician the customer chooses.
| Step | Who does it | What is needed |
|---|---|---|
| Connection application | The owner on e-st.lv | Desired capacity and number of phases |
| Network construction up to the boundary | Sadales tīkls | Contract and paid invoice |
| Cable to the distribution board and internal installation | Electrician | Distribution board and circuits built |
| Confirmation of readiness | The owner on e-st.lv | Finished internal work |
| Meter installation | Sadales tīkls | Contact within 2 working days after the confirmation |
Sadales tīkls states that after the internal networks have been prepared and the customer has submitted a confirmation on e-st.lv, it makes contact within 2 working days about installing the meter. The confirmation is not a measurement protocol, but it makes sense to check that what has been built works safely before submitting it. For the whole route, see the page new Sadales tīkls connection.
Checked on 25 November 2026: Sadales tīkls, “Permanent connection”; confirmation on e-st.lv and contact about the meter within 2 working days.
Access to Trīsciems is via Jaunciema gatve and local roads, and the choice of public transport is more limited. If the plot has no address sign yet, write the cadastral number in the form or attach the location on a map, so that the right place is found quickly for the site visit.
A garden house getting electricity for the first time
If a garden plot has had no electricity so far, the garden house is the first building to get a distribution board. Then it is worth thinking ahead: whether there will later be a dwelling house, sauna or charger on the plot. The board and number of phases are chosen accordingly, and the as-built diagram shows from the start where the cables run and which circuits are where.
If the garden house is later put into use or altered, this diagram and the first measurements make the papers easier. For how electrical documents for a garden house differ from those for a dwelling house, see the page electrical documents for a garden house.
A sauna, garage or shed with its own line
On detached house plots in Trīsciems there may be a sauna, garage or shed next to the house. If they are fed from the house distribution board, the line to them is part of the house installation and is measured with the house. If an outbuilding has its own board, the measurement report describes it as a separate part with its own circuits.
A sauna has a damp environment and a heater, so the test pays special attention to the residual current device (RCD) and its operation. In a garage or shed, earthing and cable condition matter, especially if the cable runs underground. For what outbuilding papers contain, see the page electrical documents for a sauna, garage or outbuilding. In your request, write how far the building is from the house and whether the cable is laid underground.
Houses you built yourself: what has to be measured
If a second-group residential house has been built by the owner, electrical installation test documentation is needed for acceptance into use (Building Construction Regulations, points 157.7.1 and 168.1). This applies to a self-built house, not to every detached house. If a construction company with a construction manager built the house, the electrical documents are part of its as-built documentation, and ask it for them first.
In a self-built house the whole installation is measured:
- insulation resistance for each circuit before it is switched into use;
- phase-neutral loop impedance, to see whether the circuit breakers will disconnect a fault;
- earthing resistance and the protective conductor bond to the parts to be earthed;
- operation of residual current devices.
It is worth ordering an as-built diagram together with the measurements to show what was actually built, because for a self-built house the design diagram and reality may differ. For the full list, see the page electrical documents for a self-built house. In Riga, putting into use is handled by the municipality’s City Development Department, and in cases started after 31 December 2019 the application can be submitted in BIS.
Price for connection papers, a house and a diagram
For work and documents for Sadales tīkls the price is set after the site visit: it is determined by whether the incoming supply and board already suit the required capacity and whether measurements are needed. Measurements and documentation for putting a private house into use cost from €230. For an as-built diagram the price is set after the site visit, because the number of boards and circuits and the cable routes to be traced on site matter. For a sauna or shed we tell you the scope and price after the site visit. The site visit is paid: €40.
Prices cover the electrician’s work and the documents. Sadales tīkls and building authority fees are separate. The documents are prepared and signed by a certified electrical specialist.
Sources
- Confirmation on e-st.lv after the internal networks are prepared; contact about the meter within 2 working days; boundary at the Sadales tīkls distribution cabinet checked 25 November 2026
- Building Construction Regulations, points 157.7.1 and 168.1: electrical installation test documentation for a self-built house checked 25 November 2026
- In Riga acceptance into use is handled by the City Development Department; in cases after 31 December 2019 the application goes through BIS checked 25 November 2026